A broken Primavera P6 schedule is one you can no longer trust to tell you what will happen next. The fix isn't to drag activities around until the finish date looks right. It's to diagnose why the logic stopped working, rebuild it properly, and put governance in place so it doesn't happen again. Below is the process we use when a client hands us a programme that's stopped behaving.

What Does a “Broken” P6 Schedule Actually Mean?

It's not one thing. It's usually a combination of:

If you want an objective read on which of these apply, run a DCMA 14-point assessment first. We've written a full walkthrough of that check with a P6 example: The DCMA 14-Point Schedule Assessment, Explained. It turns “this schedule feels wrong” into a scored list of exactly what's wrong, which is where recovery should start.

Recovery Schedule or Revised Schedule: Which Do You Need?

This distinction gets muddled online, and it matters before you touch a single date.

A recovery schedule keeps the original contractual completion date and re-plans how the remaining work gets there. It's an acceleration and re-sequencing exercise, not a renegotiation.

A revised schedule accepts that the completion date itself needs to move, usually because delay has already eaten the float and no realistic re-sequencing gets you back to the original date.

Confusing the two causes real problems on UK contracts. Under NEC4, for example, a revised programme submitted under clause 32 needs to show the effect of implemented compensation events on the dates, not paper over them with an optimistic recovery plan the contract administrator won't accept. Decide honestly, before you start rebuilding, which one you're actually producing. If the answer isn't clear yet, that's a sign you need the diagnosis in step one before committing to either.

Step 1: Diagnose Before You Touch a Single Date

Resist the urge to start dragging bars. Run the health check first (the Free P6 Check tool does this from an .xer or .xml export in your browser, nothing uploaded to a server) and get a clear list of:

This tells you whether you're dealing with a logic problem, an update discipline problem, or both. They need different fixes.

Step 2: Rebuild the Logic, Not Just the Dates

Once you know where the gaps are:

This is the slow part, and it's the part that actually determines whether the recovery plan is credible or just cosmetic.

Step 3: Re-Baseline With Governance, Not Guesswork

Once the logic is sound and the plan is genuinely achievable, set a new baseline. But do it with a paper trail:

Silent re-baselining, where the finish date resets without anyone formally agreeing it, is how schedules end up broken again within a month.

Step 4: Stress-Test the Recovery Plan Before You Submit It

A recovery plan that only works on paper isn't a recovery plan. Before it goes anywhere near a client or contract administrator:

Step 5: Stop It Happening Again

Recovery is wasted effort if the schedule drifts back into the same state in eight weeks. Put a light monthly discipline in place: a quick DCMA-style check at each update, a rule that constraints need a documented reason, and a named person who owns baseline changes rather than everyone editing freely. None of this needs to be heavy. It needs to be consistent.

When Should You Bring in Outside Help Instead of Fixing It Yourself?

If the diagnosis shows isolated issues, a competent in-house planner with a clear afternoon can usually fix it. Bring in outside help when the schedule underpins a live claim or a contractual submission, when the in-house team is too close to the programme to be objective about what's gone wrong, or when the recovery plan needs to stand up to independent scrutiny from a client, funder or the other side of a dispute. That's usually a sign the fix needs a second set of senior, independent eyes rather than another attempt from inside the same team that built the problem.

Planned works as that second set of eyes: Primavera P6 consultancy, remote-first, across construction, energy and infrastructure. If you'd rather have someone run the diagnosis and rebuild for you, book a free consultation, or start with the Free P6 Check to see where things stand.

Frequently Asked Questions

What's the difference between a recovery schedule and a revised schedule in P6?

A recovery schedule keeps the original contractual completion date and re-sequences the remaining work to hit it. A revised schedule accepts that the completion date itself has to change, usually because the float available for recovery has already gone. Which one you're producing should be decided before you start rebuilding, not discovered halfway through.

How do I know if my P6 schedule needs recovery?

Run a DCMA-style 14-point check. High out-of-sequence percentages, widespread missing logic, excessive hard constraints and negative float on activities that shouldn't have any are the clearest signs. If several of those show up together, the schedule needs a proper diagnosis and rebuild, not just a date shuffle.

Can I recover a schedule without changing the completion date?

Sometimes, if there's enough float left in the plan and the remaining work can genuinely be re-sequenced or accelerated. If the float's already gone, forcing the original date through the tool just produces a schedule that looks fine and fails on site. At that point you're looking at a revised schedule, not a recovery schedule.

How long does it take to recover a broken P6 schedule?

It depends on the scale of the logic problems, not the size of the project. A schedule with a handful of missing ties and a few stray constraints can be fixed in a day or two. One with widespread out-of-sequence progress and no clear critical path usually needs a proper diagnostic pass first, then a rebuild measured in days rather than hours.

Does a recovery schedule need approval from the client or contract administrator?

On most standard forms, yes. Under NEC4, for example, a revised programme goes to the project manager for acceptance under clause 32, with reasons recorded if it's rejected. Even where the contract doesn't strictly require it, getting formal sign-off before a recovery plan becomes the new baseline protects you if the recovery doesn't hold and the dates are challenged later.

About Planned Limited

Planned Limited specialises in project planning and scheduling for complex programmes across construction, infrastructure, energy, technology, and public sector. Our team combines decades of real-world scheduling experience with expert knowledge of industry-standard tools and best practices. We work as collaborative partners, delivering not just better schedules but improved scheduling discipline within organisations.

Meet Our Team